Inglewood is in the final year of Neighbourhood Renewal construction! If you live within the Phase 3 area, you’ve likely already received a pamphlet in the mail from the City about the schedule, access impacts, and more! In case you missed it, construction is tentatively scheduled to start this coming week, May 3.
For a breakdown of the planned projects by number in the neighbourhood, please see the Project Map (shown above).
The removal and replacement of public sidewalks, curbs and gutters and roadways is complete in projects 10, 11, 12, 13, 14 and 15. Not all the sod in projects 13, 14 and 15 was installed so we will be returning in early spring to finish the landscaping.
The outstanding landscaping from 2019 is complete (projects 10, 11 and 12).
Street lighting in projects 12, 13, 14, and 15 is ongoing and includes running new conduit, drilling new pole bases, then installing new poles and re-energizing the lights. EPCOR is energizing the new poles and completing their quality control checks while removing the old pole bases; this work will continue through 2021.
Neighbourhood renewal work will resume in Inglewood in May 2021, weather pending. Prior to work resuming, construction notifications will be delivered to impacted residences. We are pleased to report that, with the completion of 2020 work, Inglewood remains on schedule with a planned completion date of November 2021.
For more information about what to expect during construction, please visit: edmonton.ca/BuildingInglewood